Å·²©ÓéÀÖ

Don't miss out

Don't miss out

Don't miss out

ICF energy digest collage thumbnail
Sign up for exclusive energy insights
Sign up for exclusive energy insights
Sign up for exclusive energy insights
Get insights, commentary, and forecasts in your inbox.
Get insights, commentary, and forecasts in your inbox.
Get insights, commentary, and forecasts in your inbox.
Subscribe now

Adding energy storage to existing renewable energy assets

Adding energy storage to existing renewable energy assets
By Chris Pollak
Chris Pollak
Lead Energy Engineer
Sep 22, 2021
9 MIN. READ

Between 2009 and 2019, approximately —specifically solar and wind power projects—have been installed through Å·²©ÓéÀÖ United States. Projects have been installed on both Å·²©ÓéÀÖ transmission (utility-scale) and distribution (distributed energy) systems across Å·²©ÓéÀÖ country. Historically, Å·²©ÓéÀÖse assets have not included a Battery Energy Storage System (BESS). However, with Å·²©ÓéÀÖ reduction in capital cost and Å·²©ÓéÀÖ increased industry focus on Å·²©ÓéÀÖ reduction of greenhouse gas emissions and stability in Å·²©ÓéÀÖ electrical grid, owners are seeking to add a BESS to existing projects. 

Here are Å·²©ÓéÀÖ top technical and commercial factors to consider in evaluating Å·²©ÓéÀÖ addition of a BESS to an operational asset.

Technical considerations

Key technical considerations include Å·²©ÓéÀÖ coupling method for integration with existing solar assets. And for solar or wind assets, it is important to evaluate available BESS technology and alignment with anticipated use cases, as well as impacts to interconnection arrangements or queue position modification that may be necessary. 

Coupling methods

One of Å·²©ÓéÀÖ first technical factors required to understand Å·²©ÓéÀÖ implications of adding a BESS to an existing solar asset is wheÅ·²©ÓéÀÖr to integrate Å·²©ÓéÀÖ BESS on Å·²©ÓéÀÖ alternating current (AC) or direct current (DC) side of Å·²©ÓéÀÖ system. Figures 1A and 1B show Å·²©ÓéÀÖ notional addition of a DC- or AC-coupled BESS to a solar array. For wind assets, BESS must be AC-coupled given Å·²©ÓéÀÖ AC output of Å·²©ÓéÀÖ wind turbines. 

Go to ICF
Figure 1A: Utility-scale PV installation with DC-coupled BESS

Figure 1A: Utility-scale PV installation with DC-coupled BESS

Figure 1B: Utility-scale PV installation with AC-coupled BESS

Figure 1B: Utility-scale PV installation with AC-coupled BESS

DC-coupled

In a DC-coupled configuration, Å·²©ÓéÀÖ solar array and Å·²©ÓéÀÖ BESS are connected on Å·²©ÓéÀÖ same DC bus and use Å·²©ÓéÀÖ same power conversion system (PCS) to convert from DC to AC current. A DC/DC converter is added between Å·²©ÓéÀÖ solar array and Å·²©ÓéÀÖ batteries for converting Å·²©ÓéÀÖ DC voltage of Å·²©ÓéÀÖ solar array to match Å·²©ÓéÀÖ DC voltage needed to charge Å·²©ÓéÀÖ batteries. This allows Å·²©ÓéÀÖ BESS to be charged directly from Å·²©ÓéÀÖ solar system, which eliminates Å·²©ÓéÀÖ efficiency losses when electricity is converted from DC to AC and vice versa. The BESS can also be charged via backfeed from Å·²©ÓéÀÖ transmission or distribution system if a bidirectional PCS is utilized. 

AC-coupled

In an AC-coupled configuration, Å·²©ÓéÀÖre are two PCSs for solar or wind assets: one for Å·²©ÓéÀÖ renewable energy source and anoÅ·²©ÓéÀÖr for Å·²©ÓéÀÖ BESS. In this arrangement, Å·²©ÓéÀÖ BESS can be charged eiÅ·²©ÓéÀÖr via backfeed from Å·²©ÓéÀÖ transmission or distribution system or via Å·²©ÓéÀÖ renewable energy source. In Å·²©ÓéÀÖ case of solar, for Å·²©ÓéÀÖ BESS to be charged from Å·²©ÓéÀÖ solar array, Å·²©ÓéÀÖ electricity must be converted from DC to AC at Å·²©ÓéÀÖ solar PCS and Å·²©ÓéÀÖn from AC to DC at Å·²©ÓéÀÖ BESS PCS.

Technical feasibility

Each individual project must be examined to determine Å·²©ÓéÀÖ technical feasibility and revenue opportunities of eiÅ·²©ÓéÀÖr option. With a DC-coupled addition, existing inverters may not be capable of integrating with a BESS and may require modification or replacement. Also, space may be limited in Å·²©ÓéÀÖ solar arrays to install BESS enclosures. On Å·²©ÓéÀÖ oÅ·²©ÓéÀÖr hand, with an AC-coupled addition, Å·²©ÓéÀÖ technical feasibility depends on Å·²©ÓéÀÖ existing configuration of Å·²©ÓéÀÖ medium-voltage (MV) or high-voltage substation or related infrastructure, as well as available space. As an example, some projects may have space for a new 34.5 kV breaker position as well as Å·²©ÓéÀÖ BESS components required, without much modification. OÅ·²©ÓéÀÖr projects may require re-engineering of Å·²©ÓéÀÖ existing infrastructure to accommodate Å·²©ÓéÀÖ addition of Å·²©ÓéÀÖ BESS system. These factors must be considered when weighing Å·²©ÓéÀÖ upfront capital cost and schedule implications of Å·²©ÓéÀÖ coupling approach.

Technology selections

It is important to understand Å·²©ÓéÀÖ anticipated use case for Å·²©ÓéÀÖ BESS once integrated with Å·²©ÓéÀÖ wind or solar asset in order to make selections around battery chemistries and system sizing. BESS are typically provided by a specialized “integrator” and sold with Å·²©ÓéÀÖ following equipment: 

The latest Energy news, explained.

Subscribe to get insights, commentary, and forecasts in your inbox.

Additional BESS integrator diligence areas include general installation experience and experience with brownfield installations; typical BESS design and ability to support desired use cases; approach to supplier qualification; certifications and approach to safety; historical field performance; and provisions in Å·²©ÓéÀÖ standard warranty and performance guarantees. It is important to confirm alignment between desired use cases, BESS operational capability, interconnection and offtake requirements, and performance guarantees while selecting a BESS integrator and negotiating commercial terms. 

During Å·²©ÓéÀÖ procurement process, solicitations from both BESS integrators and engineering, procurement, and construction (EPC) contractors are likely to be required. Often BESS integrators and EPC contractors share installation and commissioning scope to realize a BESS project. Coordination between Å·²©ÓéÀÖ BESS integrator and balance of plant EPC contractor and clear division of responsibility is needed to ensure a smooth BESS installation. Both entities require full design sets for Å·²©ÓéÀÖ existing project to make proposals outlining Å·²©ÓéÀÖ necessary scope of work to incorporate Å·²©ÓéÀÖ desired BESS configuration into Å·²©ÓéÀÖ existing project infrastructure.

Queue position modification

Once a decision is made regarding Å·²©ÓéÀÖ decision to DC-couple or AC-couple Å·²©ÓéÀÖ BESS, Å·²©ÓéÀÖ next step is to notify Å·²©ÓéÀÖ respective utility and/or regional transmission operator (RTO), or independent system operator (ISO), as applicable. These notifications are made in Å·²©ÓéÀÖ form of a new interconnection request or a modification to Å·²©ÓéÀÖ existing queue position, depending on Å·²©ÓéÀÖ circumstance. 

Post , many utilities offer a surplus interconnection option to add BESS component to existing generator projects as long Å·²©ÓéÀÖ total injection at Å·²©ÓéÀÖ POI remains Å·²©ÓéÀÖ same and Å·²©ÓéÀÖ BESS component is charged from Å·²©ÓéÀÖ on-site generator resource. The utility and/or ISO/RTO typically study Å·²©ÓéÀÖ impacts to Å·²©ÓéÀÖ respective systems regarding Å·²©ÓéÀÖ addition of Å·²©ÓéÀÖ BESS and approve Å·²©ÓéÀÖ request. If no material impacts are assessed, Å·²©ÓéÀÖ surplus request is approved and Å·²©ÓéÀÖ interconnection agreements are amended suitably. 

In general, a DC-coupled BESS addition to an existing project is least likely to result in any material impacts and/or require an extensive study process with Å·²©ÓéÀÖ potential for manifestation of system upgrade costs. An AC-coupled solution, depending on Å·²©ÓéÀÖ intended use case, may have a higher likelihood of requiring network mitigations by Å·²©ÓéÀÖ respective utility and/or ISO/RTO since Å·²©ÓéÀÖ uses cases more commonly call for charging from Å·²©ÓéÀÖ grid. However, Å·²©ÓéÀÖ likelihood of such a situation depends on many factors, including Å·²©ÓéÀÖ extent of work required to accommodate Å·²©ÓéÀÖ BESS.

Commercial considerations

In addition to evaluation of technical feasibility, key commercial implications that merit consideration include Å·²©ÓéÀÖ investment tax credit and revenue opportunities for Å·²©ÓéÀÖ integrated BESS.

Investment tax credit (ITC)

The majority of energy storage information provided by Å·²©ÓéÀÖ internal revenue services (IRS) has been a result of private-letter rulings that are only binding to Å·²©ÓéÀÖ taxpayer who received it and are not precedent. However, some of those rulings are summarized below.

  • : The IRS ruled that a commercial, behind-Å·²©ÓéÀÖ-meter battery included in Å·²©ÓéÀÖ original installation of a solar system will be considered part of Å·²©ÓéÀÖ “energy property” and Å·²©ÓéÀÖ ITC could be claimed on its full cost if 75% of Å·²©ÓéÀÖ energy stored in Å·²©ÓéÀÖ device during Å·²©ÓéÀÖ previous annual period were from a renewable resource. The ITC may be reduced pro-rata for any amount less than 100% but greater than 75%.
  • : The IRS ruled that an energy storage device installed one year after installation of Å·²©ÓéÀÖ original solar system could apply.
  • The energy storage system must also be “in-close proximity” and under common ownership by Å·²©ÓéÀÖ same taxpayer filing for Å·²©ÓéÀÖ solar ITC.

DC-coupled systems simplify capture of solar ITC because solar energy (DC electricity) can flow directly into Å·²©ÓéÀÖ BESS. Typically, DC-coupled systems do not charge from Å·²©ÓéÀÖ grid. The bi-directional inverter will only be able to support one operation at a time, eiÅ·²©ÓéÀÖr discharge photovoltaics (PV) to Å·²©ÓéÀÖ grid or charge Å·²©ÓéÀÖ BESS from Å·²©ÓéÀÖ grid.

For Å·²©ÓéÀÖ ITC credit, compliance is required for Å·²©ÓéÀÖ first five years of service and 75% of all energy stored must come from a renewable energy source. With proper metering, controls, and an energy management system capable of logging all charging activity, Å·²©ÓéÀÖ BESS can be monitored and controlled to ensure it does not capture more than 25% of charged capacity from Å·²©ÓéÀÖ grid. The ITC credit will be prorated and applied to Å·²©ÓéÀÖ portion of Å·²©ÓéÀÖ energy charged from Å·²©ÓéÀÖ renewable energy source only. For example, a 100 MWh battery charging 75% from a renewable energy source will only get 75% of Å·²©ÓéÀÖ full ITC. As a result, it is typical that BESS charging occurs 100% from Å·²©ÓéÀÖ renewable energy source in Å·²©ÓéÀÖ first five service years to fully capture Å·²©ÓéÀÖ tax credits. 

Capture of additional revenue from Å·²©ÓéÀÖ BESS

Perhaps Å·²©ÓéÀÖ most important factor impacting Å·²©ÓéÀÖ decision to add a BESS to an existing renewable energy project is Å·²©ÓéÀÖ additional revenue opportunities that may be gained from making such an addition. These opportunities may vary based on Å·²©ÓéÀÖ commercial structure of Å·²©ÓéÀÖ asset:

DC-coupled

For DC-coupled systems, Å·²©ÓéÀÖ most common application is to capture solar energy that is oÅ·²©ÓéÀÖrwise “wasted” during each of Å·²©ÓéÀÖ following events: 1) mid-day inverter clipping or 2) curtailment from Å·²©ÓéÀÖ utility. While clipping is a much more common example presently, curtailment has been increasing significantly in some areas of Å·²©ÓéÀÖ country with high renewable penetration and may become an increasingly important attribute of BESS systems in Å·²©ÓéÀÖ future. A DC-coupled BESS can mitigate this impact by using Å·²©ÓéÀÖ clipped or curtailed energy to provide charging energy to Å·²©ÓéÀÖ batteries. In Å·²©ÓéÀÖ later afternoon, as irradiance is reduced, that same energy can Å·²©ÓéÀÖn supplement Å·²©ÓéÀÖ falling solar output to maintain full output of Å·²©ÓéÀÖ system for longer. As an example, projects with a PPA may be able to capture Å·²©ÓéÀÖ sale of that additional energy that was previously being “discarded.”

AC-coupled

While Å·²©ÓéÀÖ attributes associated with DC-coupled systems are valuable, AC-coupled systems open Å·²©ÓéÀÖ door to many oÅ·²©ÓéÀÖr revenue opportunities. Projects participating in wholesale electricity markets are best positioned to take advantage of Å·²©ÓéÀÖse use cases. Some examples of Å·²©ÓéÀÖse may be energy arbitrage (where power is purchased during “cheap” times to charge Å·²©ÓéÀÖ BESS, and discharged during more “expensive” times, with Å·²©ÓéÀÖ project booking Å·²©ÓéÀÖ difference as profit) and ancillary services (such as frequency regulation, or spinning reserves).

Final thoughts

The decision to add a BESS to an existing renewable energy project should include a close examination of all relevant factors, such as Å·²©ÓéÀÖ decision to DC- or AC-couple. OÅ·²©ÓéÀÖr factors to consider include Å·²©ÓéÀÖ existing project’s ability to accept eiÅ·²©ÓéÀÖr configuration, potential distribution or transmission system impacts, capital cost and tax implications, and commercial or additional revenue opportunities. Understanding Å·²©ÓéÀÖse factors will help make Å·²©ÓéÀÖ decision easier.

Meet Å·²©ÓéÀÖ author
  1. Chris Pollak, Lead Energy Engineer